Railcar Unloading
Facility designed to receive feed stock via railcar
RDS responsible for FEED and Detail Design
RCI responsible for Construction Management
Crude by Rail
Facility designed to receive feedstock via railcar
RDS responsible for FEED and Detail Design (ISBL)
RCI responsible for fabrication of the pipe and modules for unloading rack facility
RCI scheduled to perform construction management once permitting is complete
Railcar Crude Unloading
Civil, ME, Process, E/I and Pipe designers
RDS responsible for FEED and Detail Design
Crude by Rail
RIG responsible for design/overall layout of track system
Design and installation of the sub-ballast portion of the track
Performing all Phase 4 Engineering, Procurement, Fabrication and Construction for ISBL and OSBL
Unloading rack prefabricated as modules at the RCI construction yard and shipped to site to be erected.
