GREEN DIESEL HYDROTREATER – LA

10K BPSD Green Diesel Hydrotreater

  • Joint venture execution
  • UOP licensed technology
  • Green Diesel Hydrotreater, Pre-Treating Facility, Tankage, Rail Off-Loading and Offsites
  • Fast-paced schedule – detailed engineering and design schedule of only 12 months
  • Overall schedule – 22 months
  • Complex rail off-loading scheme: frozen tallow and grease from all parts of the country arriving at varying temperatures
  • Purchased 420 pieces of tagged equipment and instruments
  • 12 storage tanks
  • Responsible for shop inspection and expediting
  • Overall construction management
  • Civil construction responsibilities:
    • 4,000 timber piles
    • 15,000 cubic yards of concrete
    • 16,000 linear feet of underground pipe
  • Mechanical, electrical and instrumentation by joint venture partner

Total RDS Engineering and Design man-hours: 200,000