HYDROCRACKING UNIT – LA

50K BPSD Hydrocracking Unit

  • SC Shell licensed technology
  • Includes HCU, Light Ends Unit (LEU), Sour Water Stripper (SWS), Amine Treating Unit (ATU) and associated Offsites (OSBL)
    • HCU included 33 piperack modules (super modules)
    • LEU contained 9 piperack modules (super modules)
    • SWS, ARU and cooling Tower Units all stick built
  • Overall Construction Management Responsibilities
  • Direct hire Mechanical construction execution
  • Developed scheme to offload reactors that shortened construction schedule
  • Over 250,000 detailed design and engineering man-hours
  • 1,200,000 construction man-hours

Total RIG man-hours: approximately 1,450,000