Railcar Unloading Facility designed to receive feed stock via railcar RDS responsible for FEED and Detail Design RCI responsible for Construction Management Crude by Rail Facility designed to receive feedstock via railcar RDS responsible for FEED and Detail Design (ISBL) RCI responsible for fabrication of the pipe and modules for unloading rack facility RCI scheduled to perform construction management once permitting is complete Railcar Crude Unloading Civil, ME, Process, E/I and Pipe designers RDS responsible for FEED and Detail Design Crude by Rail RIG responsible for design/overall layout of track system Design and installation of the sub-ballast portion of the track Performing all Phase 4 Engineering, Procurement, Fabrication and Construction for ISBL and OSBL Unloading rack prefabricated as modules at the RCI construction yard and shipped to site to be erected.