GREEN DIESEL HYDROTREATER – LA

10K BPSD Green Diesel Hydrotreater

Joint venture execution
UOP licensed technology
Green Diesel Hydrotreater, Pre-Treating Facility, Tankage, Rail Off-Loading and Offsites
Fast-paced schedule - detailed engineering and design schedule of only 12 months
Overall schedule - 22 months
Complex rail off-loading scheme: frozen tallow and grease from all parts of the country arriving at varying temperatures
Purchased 420 pieces of tagged equipment and instruments
12 storage tanks
Responsible for shop inspection and expediting
Overall construction management
Mechanical, electrical and instrumentation by joint venture partner

Civil construction responsibilities:

4,000 timber piles
15,000 cubic yards of concrete
16,000 linear feet of underground pipe
  • Total RDS Engineering and Design man-hours: 200,000